Every permit office for a metal building in six Central Texas counties

Six counties, and six different answers to the same question.

Deep cracks in dry Blackland clay soil in a Central Texas field. Illustrative photograph, not a project record.

This sheet puts all of them side by side: who issues a building permit outside the city limits, who administers the floodplain, who permits the septic system, who permits the driveway, and whether the Edwards Aquifer program reaches that county. Each answer is that county's own, with the page it came from and the day it was read.

Keep reading

Where a county publishes nothing on a subject, the cell says so in the county's own terms rather than filling the gap with a guess. The cities inside these counties run their own permits, so a second table carries the ones whose pages were read.

The six counties, outside the cities

One row per county, from that county's official site. A cell reading "Read, not listed" means the county publishes no such permit, which is not the same as saying none applies.
County Inside a city Outside the cities Edwards Aquifer Source
Travis County Austin, Bee Cave, West Lake Hills: Commercial plan review, seven to 20 business days by size. Also Pflugerville, Lakeway, Manor, Lago Vista, Jonestown, Sunset Valley, Rollingwood, each running its own permits. County development permit, plus a Fire Marshal permit for a commercial building Named by the TCEQ program pages. Which zone a parcel sits on is settled at TCEQ's own maps, not here. Travis County TNR Development Services, Commercial Site Plan, read 2026-09-20
Williamson County Georgetown, Round Rock, Leander, Cedar Park, Hutto, Taylor, Liberty Hill: Commercial building permit, 30 business day review. Also Jarrell, each running its own permits. Read, not listed. No county building permit, building code or certificate of occupancy Named by the TCEQ program pages. Which zone a parcel sits on is settled at TCEQ's own maps, not here. Williamson County, frequently asked questions, infrastructure and developers, read 2026-09-20
Bastrop County Bastrop, Elgin, Smithville: City building permit after site development plan approval. County development permit for any external development; no building permit or CO The TCEQ program pages read do not name this county. Confirm with the Austin Regional Office before assuming either way. Bastrop County Development Services, and the Development Services application fees, read 2026-09-20
Caldwell County Luling: City permit for all construction, storage buildings named. Also Lockhart, Martindale, Mustang Ridge, Uhland, Niederwald, each running its own permits. County site construction permit for commercial work; no county building code The TCEQ program pages read do not name this county. Confirm with the Austin Regional Office before assuming either way. Caldwell County Development Ordinance, revised February 14, 2023, and the subdivision and development fee schedule, read 2026-09-20
Lee County Giddings: City permit with fees listed for commercial and storage buildings. Also Lexington, Dime Box, each running its own permits. County development permit for any structure over 100 square feet The TCEQ program pages read do not name this county. Confirm with the Austin Regional Office before assuming either way. Lee County Development Services Department, read 2026-09-20
Burnet County Burnet, Marble Falls, Bertram, Granite Shoals: City building permit for any added structure. Also Horseshoe Bay, Cottonwood Shores, each running its own permits. County building permit: Class A $25, Class B $400 inside a flood hazard boundary The TCEQ program pages read do not name this county. Confirm with the Austin Regional Office before assuming either way. Burnet County, on-site sewage facilities and development permits, read 2026-09-20

The Edwards Aquifer column reads from the TCEQ program pages: TCEQ names eight counties for the Edwards Aquifer Protection Program. Texas Commission on Environmental Quality, Edwards Aquifer Protection Program, read 2026-09-20.

Who to call, permit by permit

The office each county names for each permit, with the number its own page publishes. An empty cell means that county's site lists no such office.
County Building permit Floodplain Septic (OSSF) Driveway
Travis County Travis County Transportation and Natural Resources, Development Services, Permit Desk
(512) 854-4215
Travis County Transportation and Natural Resources, Floodplain Administrator
(512) 854-4215
Travis County Transportation and Natural Resources, Development Services
(512) 854-4215
Travis County Transportation and Natural Resources, Development Services
(512) 854-4215
Williamson County Read, not listed. Williamson County Engineer, Road and Bridge Division, 3151 SE Inner Loop, Georgetown
(512) 943-3330
Williamson County Engineer's Office, Floodplain Administrator
(512) 943-3330
Williamson County Engineer's Office, OSSF program, 3151 SE Inner Loop, Suite B, Georgetown
(512) 943-3330
Williamson County Engineer, Road and Bridge Division
(512) 943-3330
Bastrop County Bastrop County Development Services, 211 Jackson Street, Bastrop
(512) 581-7176
Bastrop County Development Services, Floodplain Administrator
(512) 581-7159
Bastrop County Development Services, Environmental and Sanitation, 211 Jackson Street
(512) 581-4042
Bastrop County Development Services
(512) 581-7176
Caldwell County Caldwell County Sanitation and Development Services, 1700 FM 2720, Lockhart
(512) 398-1803
Caldwell County Sanitation and Development Services, Floodplain Administrator
(512) 398-1803
Caldwell County Sanitation and Development Services, 1700 FM 2720, Lockhart
(512) 398-1803
Caldwell County Sanitation and Development Services
(512) 398-1803
Lee County Lee County Development Services, Lee County Annex, Giddings
(979) 542-3178
Lee County Judge's Office, Floodplain Administrator, 200 South Main, Room 107, Giddings
(979) 542-3178
Lee County Sanitation, at Development Services, 200 S Main St, Room 203, Giddings
(979) 212-8070
Lee County Development Services, with the precinct commissioner
(979) 542-3178
Burnet County Burnet County Development Services, 220 S Pierce Street, Burnet
(512) 756-5445
Burnet County Development Services
(512) 756-5445
Burnet County Development Services, 220 S Pierce Street, Burnet; LCRA on the lakes
(512) 756-5437
Read, not listed. Burnet County Development Services
(512) 756-5420

The cities, each running its own permits

The cities inside these six counties whose own permit pages were read. A city not listed here still runs its own permits; call the city before assuming the county answer applies.
City County What the city's own page says Department Source
Austin Travis Commercial plan review, seven to 20 business days by size City of Austin Development Services, 6310 Wilhelmina Delco Drive, (512) 978-4000 City of Austin Development Services, 6310 Wilhelmina Delco Drive, read 2026-09-20
Bee Cave Travis Building permit and plan review City of Bee Cave Planning and Development, (512) 767-6675 City of Bee Cave Planning and Development, read 2026-09-20
West Lake Hills Travis Commercial building permit, first comments in up to four weeks City of West Lake Hills Building and Development Services, (512) 327-3628 City of West Lake Hills Building and Development Services, read 2026-09-20
Georgetown Williamson Commercial building permit, 30 business day review City of Georgetown Building Inspections, 300-1 Industrial Ave., (512) 930-2550 City of Georgetown Building Inspections, 300-1 Industrial Ave., read 2026-09-20
Round Rock Williamson Building permit for any structure, four to eight week review City of Round Rock Building Inspection Division City of Round Rock Building Inspection Division, read 2026-09-20
Leander Williamson Permit before any construction inside the city City of Leander Development Services City of Leander Development Services, read 2026-09-20
Cedar Park Williamson Permit for any structure, 11 working days to first comments City of Cedar Park Building Permits and Inspections, 450 Cypress Creek Road, (512) 401-5100 City of Cedar Park Building Permits and Inspections, 450 Cypress Creek Road, read 2026-09-20
Hutto Williamson Permit for new commercial construction, 15 business days to comments City of Hutto Permits and Inspections Division City of Hutto Permits and Inspections Division, read 2026-09-20
Taylor Williamson Commercial permit at $1.00 per square foot plus review City of Taylor Development Services City of Taylor Development Services, read 2026-09-20
Liberty Hill Williamson Building permit for any added structure City of Liberty Hill Building Permits and Inspections City of Liberty Hill Building Permits and Inspections, read 2026-09-20
Bastrop Bastrop City building permit after site development plan approval City of Bastrop Development Services, 1311 Chestnut Street, (512) 332-8840 City of Bastrop Development Services, 1311 Chestnut Street, read 2026-09-20
Elgin Bastrop City permit for any structure, storage units named City of Elgin Building Division, (512) 281-0119 City of Elgin Building Division, read 2026-09-20
Smithville Bastrop City permit, plan review up to ten workdays City of Smithville, City Hall, 317 Main Street, (512) 237-3282 City of Smithville, City Hall, 317 Main Street, read 2026-09-20
Luling Caldwell City permit for all construction, storage buildings named City of Luling permits and inspections, 509 E. Crockett St. (mailing), 2510 E. Pierce St. (physical), (830) 875-2481 City of Luling permits and inspections, 509 E. Crockett St. (mailing), 2510 E. Pierce St. (physical), read 2026-09-20
Giddings Lee City permit with fees listed for commercial and storage buildings City of Giddings Code Compliance, 118 East Richmond, (979) 540-2710 City of Giddings Code Compliance, 118 East Richmond, read 2026-09-20
Burnet Burnet City building permit for any added structure City of Burnet Building Department, 301 E Jackson St, (512) 715-3206 City of Burnet Building Department, 301 E Jackson St, read 2026-09-20
Marble Falls Burnet Building permit and commercial plan review under the 2024 codes City of Marble Falls Development Services, Building Division, 801 4th Street, (830) 798-7088 City of Marble Falls Development Services, Building Division, 801 4th Street, read 2026-09-20
Bertram Burnet Permit through a third-party plan reviewer City of Bertram Development Services, 110 East Vaughan Street, (512) 355-2197 City of Bertram Development Services, 110 East Vaughan Street, read 2026-09-20
Granite Shoals Burnet City permit at $1.25 per square foot, third-party review City of Granite Shoals Building and Development, (830) 598-2424 City of Granite Shoals Building and Development, read 2026-09-20

Also inside these six counties, each running its own permits with nothing read here yet: Pflugerville (Travis), Lakeway (Travis), Manor (Travis), Lago Vista (Travis), Jonestown (Travis), Sunset Valley (Travis), Rollingwood (Travis), Jarrell (Williamson), Lockhart (Caldwell), Martindale (Caldwell), Mustang Ridge (Caldwell), Uhland (Caldwell), Niederwald (Caldwell), Lexington (Lee), Dime Box (Lee), Horseshoe Bay (Burnet), Cottonwood Shores (Burnet).

How this sheet is kept

Every row carries the page it came from and the date it was read. Nothing on this sheet comes from a directory, an aggregator or another contractor's website.

County and city pages change. A date more than a few months old is a reason to call the office in the row rather than to trust the cell, and the source link goes straight to the page the cell was read from.

This sheet is a reading of what each office publishes. It is not legal advice, it is not a permit, and no office has reviewed it.

What each office actually reviews, and the order the whole job runs in, is on metal building permits in Austin and Travis County and building a metal building in the Austin area. Every county has its own sheet under the six counties.

Asked before pricing

Which Central Texas counties require a building permit for a metal building?

It differs by county, which is why this sheet exists. Some counties here issue a building or development permit for work outside the city limits, one issues a fire code permit through its Fire Marshal for a commercial building, and one publishes no county building permit, building code or certificate of occupancy at all. The county column on this page gives each answer in that county's own words, with the office, the phone number, the page it was read from and the date.

Does a county with no building permit mean no permit is needed?

No. A county that publishes no building permit still publishes other permits, and the state rules apply everywhere. On this footprint that can include a floodplain development permit, an on-site sewage facility permit through the county's authorized agent, a driveway permit for work in the county right of way, state accessibility registration above a cost threshold, and stormwater coverage by acreage. Each of those has its own row or its own column on this sheet.

What if the lot is inside a city?

The city permits the building and the county answer does not apply. The second table on this page carries the cities in these six counties whose own permit pages were read, with the department, the phone number and the date. A city that is not in that table still runs its own permits; the county page for that county names it, and the city is the office to confirm with before anything is designed.

How current is this directory?

Every cell carries its own read date, and the source link opens the exact page it was read from. Offices update fee schedules, adopt new code editions and reorganize their sites, so a cell is a record of what that page said on that day rather than a standing guarantee. When a date is old or the answer decides a real budget, call the office in the row and confirm it.

Free estimate, six questions

Price a metal building in the Austin area

The county tells a contractor which permit office your lot answers to. The building and the timing tell them what to look at first. Pricing it is free, and you owe nothing either way.

By submitting this form, I agree that Central Texas Metal Buildings and a metal building construction contractor may contact me at the phone number and email address I provided, including by automated phone calls and prerecorded messages, regarding metal building construction services. Consent is not a condition of any purchase. Message and data rates may apply. I may opt out at any time by asking to be removed during any call or by replying to any email. See our Privacy Policy.

Your request goes to an independent local metal building contractor serving Central Texas, not a national lead list.