Requests go to one independent metal building contractor, who decides which projects to take, and any number turns on the span, the eave height, how many sides get closed in and what the drive has to carry. Five of the six counties here list a permit for a structure outside their cities, the size where it starts differs in each, and the drive that gets a trailer off the road is usually its own permit from a different office.
Inside Giddings
City permit with fees listed for commercial and storage buildings
Giddings' Code Compliance office lists its adopted codes as the 2018 International codes, the 2017 National Electrical Code and the 2018 NFPA Life Safety Code, and its June 2024 fee schedule sets a $20 permit fee, a $25 inspection fee and a $40 re-inspection fee, with building permit fees listed for new commercial construction, carports and garages, and storage buildings.
From City of Giddings Code Compliance, 118 East Richmond (read September 20, 2026).
Lee County, outside city limits
County development permit for any structure over 100 square feet
Lee County Development Services requires a Development Permit application for all development in unincorporated Lee County, including commercial projects, for any individual structure larger than 100 square feet; a building of 100 square feet or less needs no permit, and the application is valid for one year.
From Lee County Development Services Department, and its Instructions for Application for Proposed Development, which carry the 100 square foot line and the fee schedule (read September 22, 2026).
Lee County: the city desk and the county desk, each read at its own page. The other five counties have sheets of their own. The whole record is on that county's sheet.
Open-sided, enclosed, or one of each under one roof
How often the machine moves decides the walls. Posts and a roof with a wall or two turned into the weather suit equipment that comes and goes daily, with air moving through so condensation dries off the steel. An enclosed building suits what gets locked and kept out of the sun: a coach, a boat, a sprayer, trucks with tools in them.
The common answer is both under one frame: an enclosed bay at one end, an open lean-to down the long side for the tractor.
Height is the measurement people get wrong: the constraint is the tallest thing that has to drive in, measured with whatever sits on its roof, plus the clearance the door needs. Put that number on the tape before anyone draws a frame.
Does a storage building on a ranch need engineered plans?
Often not, and the engineering statute says so twice. Occupations Code 1001.056(a)(2)(F) frees plans from engineering licensing for a single-story building within 5,000 square feet whose clear spans between supports stay at 24 feet or less across the short side, on condition that the public is offered no engineering services. Where a span runs past 24 feet, 1001.056(b) confines the requirement to the roof-supporting members (trusses, beams and the like). Separately, the same section exempts a private building used solely for farming, ranching or agriculture.
The exemption is about the plans, not the permit desk: Travis County still wants a site plan sealed by a Texas-licensed engineer with a non-residential development permit, and Caldwell County wants engineer-certified drawings. The statute also says exclusively, so a building housing a contractor's fleet is not a farm building because it stands on farmland.
FromTexas Legislature Online, Occupations Code Chapter 1001, engineers (read September 20, 2026). FromTravis County TNR Development Services, Commercial Site Plan (read September 20, 2026). FromCaldwell County Development Ordinance, revised February 14, 2023, and the subdivision and development fee schedule (read September 20, 2026).
Do equipment and RV storage buildings in Central Texas need a county permit outside the cities?
Five of the six list one, and the size where it starts is different in each. The table shows what each county publishes for its unincorporated area. Within a city limit, the permit is the city's.
Each county's own answer for its unincorporated area, read on the county sites 2026-09-20.
On a phone this table scrolls sideways.
| County | County listing past the city limits | Desk and phone |
|---|---|---|
| Lee | Development Permit for any individual structure larger than 100 square feet, valid one year; 100 square feet or less needs no permit. | Development Services, Giddings, (979) 212-8070 |
| Bastrop | Development permit for any external development; an accessory building of 25 square feet or less, on no foundation and outside the floodplain, needs none. Larger ones: $50 under 200 square feet, $100 from 200 to 1,000, $500 above. | (512) 581-7176, Development Services in Bastrop |
| Caldwell | Construction permit with engineer-certified drawings before land clearing or construction; agricultural structures not intended for common public use are excluded. | Sanitation and Development Services, Lockhart, (512) 398-1803 |
| Burnet | Building permit in two classes: Class A outside any flood hazard area, $25, no inspection of the structure; Class B inside one, $400, with an elevation certificate. | Development Services, Burnet, (512) 756-5445 |
| Travis | Development Permit: Development (Residential) for a non-habitable accessory building on a residential lot, Development (Non-Residential) with an engineer-sealed site plan for a commercial project. | TNR Development Services, (512) 854-4215 |
| Williamson | Read, not listed: no county building permits and no authority to issue a certificate of occupancy. A Certificate of Compliance checks the floodplain. | County Engineer, Road and Bridge, (512) 943-3330 |
FromLee County Development Services Department, and its Instructions for Application for Proposed Development, which carry the 100 square foot line and the fee schedule (read September 22, 2026). FromBastrop County Development Services, and the Development Services application fees (read September 20, 2026). FromCaldwell County Development Ordinance, revised February 14, 2023, and the subdivision and development fee schedule (read September 20, 2026). FromBurnet County, on-site sewage facilities and development permits (read September 20, 2026). FromTravis County TNR Development Services, Commercial Site Plan (read September 20, 2026). The source was read and does not list this. FromWilliamson County, frequently asked questions, infrastructure and developers (read September 20, 2026).
Which of those lines actually catches a storage building?
Lee County's, almost every time: the line is 100 square feet, which one tractor bay clears, and the county wants a 9-1-1 address for a new business before any county permit application. The rest of that record is on the Lee County sheet.
Caldwell County is worth a call early: its ordinance excludes agricultural structures not intended for common public use and says nothing more about that edge. Williamson County publishes an absence rather than a clearance: its site lists no county building permit, which describes that office and not your tract.
FromLee County Development Services Department, and its Instructions for Application for Proposed Development, which carry the 100 square foot line and the fee schedule (read September 22, 2026). FromCaldwell County Development Ordinance, revised February 14, 2023, and the subdivision and development fee schedule (read September 20, 2026). The source was read and does not list this. FromWilliamson County, frequently asked questions, infrastructure and developers (read September 20, 2026).
Who permits the drive the trailer comes in on?
Whoever maintains the road it meets, and here it earns early attention: what is stored has to get in and turn around. For state highway frontage the permit is TxDOT's. The owner, or the owner's authorized representative, files Form 1058 with the local district office, and the state right of way stays off limits until TxDOT has executed the permit and received 24 hours of notice. All six counties sit in the Austin District, (512) 832-7000.
On a county-maintained road it is the county, at its own price: $25 for a private drive in Lee County and $150 for a commercial one, plus $15 for every foot of culvert; $50 in Bastrop County; a Work in the Public Right-of-Way Permit in Caldwell County. Burnet County lists no driveway or culvert permit for a county road, which is what that county publishes, not a finding that none exists, so that call goes to Development Services at (512) 756-5420.
FromTexas Department of Transportation, Access Management Manual, chapter 2 section 4, permits, and the Use of Right of Way by Others Manual, access driveways (read September 20, 2026). FromTexas Department of Transportation, Austin District, and Austin District contacts and offices (read September 20, 2026). FromLee County requirements for permits to construct access driveways on county right of way (read September 20, 2026). FromBastrop County Development Services, application fees and residential driveway requirements (read September 20, 2026). FromCaldwell County Development Ordinance, revised February 14, 2023, section 4.6 and Appendix C (read September 20, 2026). The source was read and does not list this. FromBurnet County, Development Services (read September 20, 2026).
How much ground can the pad and the yard disturb before stormwater coverage applies?
One acre. General permit TXR150000 tiers construction by acreage. Below one acre, with no bigger common plan of development or sale reaching an acre, the permit does not apply. One acre to under five: small construction activity. Five acres or more: large.
A storage building reaches that line on the yard, not the roof, because the measure is disturbed ground: the pad, the turnaround a trailer needs, the new drive and the drainage work all count. What each tier asks for is on pad, grading and stormwater acreage.
FromTexas Commission on Environmental Quality, stormwater general permit for construction activities (TXR150000) (read September 20, 2026).
Power at the back of the property
The co-op whose lines reach the tract serves it, and the line out to the building is usually billed to you. Bluebonnet Electric Cooperative starts new construction with a line design appointment at (800) 842-7708; a load over 200 amps needs an electric load analysis, and a non-residential general service applicant pays all estimated extension costs above $350 per service.
Pedernales Electric Cooperative's tariff lists Burnet, Caldwell, Travis and Williamson among the counties it may serve, and not Bastrop or Lee; a new location is staked first and applied for at (877) 372-0391, with $50 membership, $50 establishment and $200 system impact fees. Oncor is the wires company in parts of Williamson County, and Bartlett Electric Cooperative serves areas of Williamson and Lee counties. Which utility holds your address is on septic, well and power hookups.
FromBluebonnet Electric Cooperative, line extensions, line design appointment, and the commercial developers package (revised June 4, 2024) (read September 20, 2026). FromPedernales Electric Cooperative, service for individual residential or commercial locations, and the tariff and business rules (read September 20, 2026). FromOncor Electric Delivery, new construction (commercial) (read September 20, 2026). FromBartlett Electric Cooperative, about us, application for service, and service fees (read September 20, 2026).
The farm loan program that names farm buildings
One program in the record names this work outright. The USDA Farm Service Agency says its Farm Ownership Loans cover the purchase of farmland, the construction of farm buildings, and improvements to existing structures and infrastructure, and applications go to the local FSA office. Amounts, terms and eligibility are the agency's to publish and change.
FromUSDA Farm Service Agency, Farm Ownership Loans, and the Farm Loans Overview fact sheet (October 2025) (read September 20, 2026).
Who builds it, and who puts a price on it?
One independent metal building contractor. Building a house and general contracting carry no state license in Texas: none of the 41 regulated industries on the Department of Licensing and Regulation's roster covers either, and the Legislature did not continue the Texas Residential Construction Commission in 2009. That is why this site calls no contractor licensed. The trades that do hold a state license, like the electrician, hold it separately.
Have four things measured first: the tallest machine that drives in, how many sides get closed, the door sizes, and where the drive meets the road. Where this building sits in the whole order is on the Austin-area metal building route. No published price exists for it; the number depends on the tract.
FromTexas Department of Licensing and Regulation, regulated industries, and the Sunset Advisory Commission on the Texas Residential Construction Commission (read September 20, 2026). FromTexas Department of Licensing and Regulation, Air Conditioning and Refrigeration Contractors and Electricians program pages (read September 20, 2026).
Questions on permits and pricing, from the record
Who builds equipment and RV storage buildings in Central Texas?
One independent metal building contractor, and a Texas professional engineer seals any sheets that need it. Texas has no state license for home builders or general contractors, so this site calls no contractor licensed, and no builder whose own site names Austin or these six counties publishes a price.
Does an open-sided equipment shed need a permit in Lee County?
Lee County Development Services requires a Development Permit for any individual structure larger than 100 square feet in the unincorporated county, commercial projects included; 100 square feet or less needs no permit. The permit is valid one year, and a 9-1-1 address is required for a new business before any county permit application.
Is a storage building on a ranch exempt from engineered plans?
The engineering statute exempts a private building used solely for farming, ranching or agriculture, and separately exempts a single-story building within 5,000 square feet, every clear span 24 feet or under across the short side, when the public is offered no engineering services. Past that span, the engineering requirement narrows to the roof-supporting members.
Do I need a driveway permit to get an RV into a storage building?
It depends on the road. A new or modified driveway on a state highway takes a TxDOT permit on Form 1058 from the Austin District, (512) 832-7000; the district has to execute the permit and take 24 hours of notice before anything touches the right of way. On a county road it is the county's: Lee County charges $25 private and $150 commercial. Burnet County lists none.
Pricing request, six fields, no charge
Pricing request: RV and equipment storage buildings
Fill it in this order: county first, since it names the permit desk; then the building; then the start window, which sets what gets looked at first.
Last stop on the routing sheet: the price
Each request is routed to one independent contractor and is not sold to any lead list.
Sources re-read September 20, 2026.