Less than the name suggests at the development desk, and a full code review at the Fire Marshal's. The county pages read state no building code edition for the development permit and describe no structural plan review by the development office. What the Non-Residential Development Checklist, revised May 11, 2023, does set are site triggers: a stormwater pollution prevention plan at one acre or more of disturbance, possible permanent water quality controls above 10,000 square feet of new impervious cover, an environmental resource inventory above 10,000 square feet of disturbance, a 45 percent impervious cover limit unless the driveway is on a state road, and a traffic impact analysis determination worksheet for a new county driveway. The FY2026 fee is $137 per non-residential application plus $1.99 per $1,000 of construction valuation outside the Austin ETJ, or $66 plus $1.99 inside it, rising on October 1, 2026 to $158 plus $2.29 per $1,000 ($76 inside the ETJ) with a new $15 IT service fee; a pre-development meeting is $543 on the new schedule.
The Fire Marshal is where a commercial metal building's plans get read against a code. Travis County Code Chapter 201, the county fire code adopted under Local Government Code Chapter 233, Subchapter C, requires plan review and a Fire Marshal building permit before construction or substantial improvement of any commercial establishment, public building or multifamily building of more than three units in the unincorporated county. The chapter was replaced effective January 1, 2026, adopts the 2021 International Fire Code with local amendments, adopts the International Building Code by reference, and makes the Fire Marshal both the county fire code official and the building code official. The definition of commercial establishment leaves out private garages, carports, sheds and agricultural buildings, so an equipment barn or a garage on a house lot is not on its list; a warehouse, a shop that runs a business or a retail building is.
The clock and the fee come from the same chapter and the statute behind it. Local Government Code 233.063 has the commissioners court issue or deny the permit within 30 days of the application, with no action in 30 days counting as approval, and the Travis County page repeats both. Permit fees are tiered by construction value from an ICC valuation table: $790 under $200,000, $790 plus $1.75 per $1,000 from $200,000 to under $1,000,000, $2,800 plus $1.00 per $1,000 from $1,000,000 to under $5,000,000, and $10,900 plus $0.50 per $1,000 at $5,000,000 or more. Plans go in as digital 24 by 36 PDFs stamped by a Texas licensed engineer through tcfmopermits.com, carrying a TNR development permit application number, so the development permit application is filed first. The final inspection begins within two business days of a written request, and a Certificate of Compliance is required before the building opens to the public. The office is at 700 Lavaca Street, Suite 1101, Austin, (512) 854-4621.
SourcesTexas Legislature Online, Local Government Code Chapter 233, county regulation of housing and other structures, read 2026-09-20; Travis County TNR Development Services, Commercial Site Plan, read 2026-09-20; Travis County TNR, non-residential development checklist, read 2026-09-20; Travis County TNR, FY2026 and FY2027 development related fee schedules, read 2026-09-20; Travis County Fire Marshal, permits and plan reviews, and Travis County Code Chapter 201, read 2026-09-20.